Temporary Works — Basement – bottom up projects.
The project required the demolition of a 10 storey building plus 2 basements within part retained sections of facade, and excavation for a third level of basement.
Read MoreThis major basement excavation 12-16m deep with a plan area 60m x 70m was required to support several new superstructure blocks up to 20 stories high.